April 5, 2019 ~
UPDATE ON AQAURION WATER MAIN REPLACEMENT
1.
Beach Avenue:
- The
Contractor has 2 crews working and has installed approximately 3,200 feet
of water main to date, about 85% installed.
- The
Contractor will start testing sections of the line and disinfecting next
week.
- The
Contractor will be working this Saturday, 4/6 from 8:00 a.m. to 4:30 p.m.,
in the area of W, X, and Y street, abutters have been notified.
- It will take a week before the first section of main is tested, and once it passes, the Contractor will begin installing services.
2.
Shallow Water Main – Phase 2:
- The
Contractor has set up the by-pass piping on Cadish Avenue, the Contractor
will be connecting the temporary services next week.
- Due
to a failed water main shutdown at S Street, Contractor is scheduled to
begin work at M Street.
- A
shutdown on Cadish Ave from M Street to P Street is scheduled for Monday,
4/6 from 9-2. Most customers are on bypass with temporary services and
will not be impacted. Customers who lose water should contact the
Contractor to be put on bypass.
- When
Aquarion can determine a way to shut main down at S Street, the Contractor
will move back to that end of the project.