Good afternoon,
As you may know,
on June 1st, the Hull BOS approved the installation of a new water
main on L Street.
The project
consists of installing 330 feet of new 6-inch ductile iron water main, new
water services, a fire hydrant, and associated appurtenances on L Street to
replace the existing 2.25” main and services. The main installation is
being done to accommodate a proposed new house and water service at 6 L Street
and would also address an undersized water main. The proposed extension
will increase the availability of fire protection for the neighborhood,
including the middle school.
Below is the
proposed schedule for construction:
Next week, the
contractor, Hub Construction, will mobilize to the area, bringing equipment as
well as material.
On Thursday
August 24th, Aquarion field staff will tap the main on Central Ave
and make the connection for the new main.
The trench on
Central Ave will be paved on Friday August 25th.
During the week
of August 28th the contractor plans to do the following:
·
Install the water main and fire hydrant on L Street.
·
Pressure test the new main
Starting on
Tuesday September 5th the main will be disinfected and flushed. A
sample will be taken to the lab and if the sample comes back clean, Aquarion
field staff will begin connecting water services on L Street to the new main
starting on Monday September 11th.
The hours of
construction will be 7am -4pm, and the contractor will have a police detail
directing traffic and keeping the public safe.
The residents
have been informed of the proposed schedule and we have been in contact with
the school department to inform them of the project and the timing.
The
contractor has been in contact with Hull DPW and will comply with their
temporary and final paving requirements.
Ronit Goldstein
Manager, Communications and Operations
Aquarion Water Company
900 Main St.
Hingham, Ma 02043