NATIONAL GRID UPDATE AS OF 8-5-17
This
week National Grid has completed approximately 80% of gas main on Main Street
and are making every effort to complete the project prior to the high school students
returning to school. We anticipate gasing in the main next week followed
by service replacement. We have also begun main installation on the
fourth location on the list; Summit/Atlantic Avenue. We anticipate
completing main installation next week followed by service placement on
Summit/Atlantic Avenue. We will have three crews working today on Main Street,
V street and Atlantic Avenue 8/5. National Grid has noted that any work on
Saturday’s cannot commence before 8:00 am.
M&X
and Riley crews have been assigned to complete the gas main replacement for the
locations below in the order listed. In addition, one National Grid in-house
crew will be addressing the following streets listed below. V Street main
installation will be completed today and National Grid will begin replacing
service on Monday 8/7.
We
have sent abutter notices for 132-158 SAMOSET AV, HUL, & HADASSAH WY.
Our contractor will also be calling in dig-safe locations for the projects
listed below and we ask that the Town plan to prioritize markings based on the
order noted below. We have added locations to the list below.
M&X
Locations
1. L Street and
Nantasket Avenue – Schedule to be in mid-September or when water replacement on
L Street complete
2. 22-72 SAMOSET AV,
HUL, MALTA ST, MANOMET AV - to be scheduled
Riley
Locations
1. 22-88 MAIN ST, HUL
- Working
2. 1 - 20 OLD COLONY
RD - Completed
3. 1-8 STONEY BEACH
RD, HUL - Completed
4. 1-12 SUMMIT AV
& ATLANTIC AV – Working
5. 132-158 SAMOSET AV,
HUL, & HADASSAH WY - to be scheduled
6. 17-23 TIERNEY AV,
HUL, 36-43 BEACON RD - to be scheduled
7. 145 - 188 ATLANTIC
AVE, HUL; 36 - 39 GUN ROCK AVE - to be scheduled
8. 29 - 50 Andrew Ave,
Hull - to be scheduled
9. 4-11 SEA VIEW AV -
to be scheduled
10. 1-9 SCHOOL ST - to
be scheduled
National
Grid Crew Locations
1. V ST (to be
completed by National Grid crew) – Working
2. 2-18 MARGINAL RD -
to be scheduled
3. 2-16 Eastern Avenue
– to be Scheduled
4. 1-2 WINDMILL CT
(179 SAMOSET AVE.) - to be Scheduled
National Grid will also begin restoration
work on projects substantially completed this year:
Once main and service are complete, we
allow a 90 day settling period prior to final paving. This is the list of
project completed this construction season.
1. Nantasket Ave –
completed 4/11/17
2. 2-4 SEVENTH ST
& NANTASKET RD –completed 5/4/17
3. 1-2 NINTH ST, HUL -
completed 6/2/17
4. 206-218 NANTASKET
RD, HUL, & CLIFTON AV - completed 6/1/17
5. 1-2 NINTH ST, HUL -
completed 6/2/17
6. 59-76 H ST –
completed - 6/22/17
7. E Street -
completed 6/28/17
8. 1 - 20 Old Colony
Rd – completed 7/13/17
9. NANTASKET RD &
Newport RD – completed 7/17/17
10. 1-8 STONEY BEACH
RD, HUL – completed 7/27/17