ROADWAY CONSTRUCTION WORK NOTICE
October
- November 2020
WHAT:
Roadway paving.
WHERE: Highland
Ave, Newton St, Western Ave, Andrew Ave, Vautrinot Ave and Mt. Pleasant Ave
WHEN:
Construction will be continuing through October and into November,
weather dependent. Schedule of work is approximate and detailed on the reverse
of this leaflet. Work hours are 7am – 5 pm.
WHY:
To make repairs and improvements to the roadway.
WHO:
T.L. Edwards (Contractor) and BETA Group (Engineer)
Impact
on Area:
All vehicles must be removed from the street
by 7:00 AM each morning. Expect traffic
detours/delays. Street parking will not be permitted during construction
activities. Access to driveways will be limited during construction
activities-please plan accordingly. Expect construction noise. Police details
will be onsite and will direct local traffic as needed.
This
information will also be posted on the Town of Hull website at www.town.hull.ma.us
and Facebook page at www.facebook.com/town-of-hull. In addition, Code Red messages will be issued
for the neighborhood.
Contacts: If you have any special
needs, deliveries, concerns, or questions, contact:
Dan
Moniz, Resident Project Representative at (508) 326 - 8406
Frequently Asked Questions (FAQs)
Q: Why is the Town completing
this Project?
A: The Town’s infrastructure is aging, and
the roadway in this area is in need of rehabilitation.
Q: How will my property be
impacted?
A: The Contractor may need to access your property to reconstruct a few feet
of your driveway and/or walkway so that there will be a
smooth transition between your drive/walk and the roadway. Also, the contractor may need to disturb the
first few feet of your lawn due so that there will be a smooth transition
between the road and your lawn. The
contractor will restore these areas as required.
Q. Will there be any excavation?
A: There will be shallow excavation (1 foot
or less) for the reconstruction of driveway aprons, if necessary.
Q:
What is the schedule?
A: The following schedule is tentative and
is weather dependent. The
approximate schedule of this work is as follows:
·
Commencing
on or about Wednesday, Oct 21 to Monday, Oct 26th :-Leveling course
paving
·
Week
of October 26th :- Raise drainage & utility covers and grates
·
Week
of November 2nd- Final paving
Q:
Who will be coming to the neighborhood?
A: T.L. Edwards will
be completing this work. All Contractors
will be clearly identified by their company
credentials or town contractor identification and vehicles.
The Town of Hull Police Details
will be onsite assisting in traffic
control and pedestrian access while work
is being completed. As is always the
case, if you have any concerns about someone in your neighborhood or on your property,
please contact the Hull Police Department at 781-925-1212
or 911.
Q: Who do I call with special
needs or in the case
of an emergency?
A: Please see the front of this letter for contact information of the representative that will be working on this project. As always, in case of an emergency, please dial 911 for
immediate assistance.